Project Name: ZIPPY SHELL TAMPA
Location: 4908 W LINEBAUGH AVE
Project Timeline: 6 Months
Completion Date: October 2025
Size/Area: 125,000 SQ FT
Mix: 4000
Owner: ZIPPY SHELL
Contractor: ARCO NATIONAL CONSTRUCTION LLC
Sub-Contractor: T & T CONSTRUCTION
Supplier: QUIKRETE CONSTRUCTION MATERIALS
Engineer: ECS
Application: TILT UP CONSTRUCTION
Fiber: 3/4 LBS
Website Links:
This tilt-up concrete project in Tampa, Florida was delivered by ARCO National Construction as the General Contractor, with QUIKRETE supplying the concrete and T&T Construction serving as the concrete subcontractor. The project utilized a 4,000 PSI mix primarily, with the slab-on-grade reinforced using ¾ lb of fiber to enhance durability and performance.rnrnCompleted in approximately six months, the project required nearly 5,000 cubic yards of concrete and highlights the efficiency and coordination of an experienced construction team.