Project Name: Pier 66
Project Timeline: Approximately 9-10 months
Completion Date: 11/23
Address: 2301 SE 6 Ave Ft Lauderdale, FL
Supplier: Supermix
Sub-Contractor: RSI
Application: SOG/Walls/Fill Cells/etc
Mix: Range from 3,000 PSI to 4,000, 5,000, 6,000, 8,000, 3,000 Lightweight
 

Pier 66 has 2 New Towers and Parking Garage. These new forever homes will have a clear view of the 17th Causeway and the Intracoastal Waterway. These beauties took approximately 40,000 yards and completed in record time of 10 months. Mixes ranged from 3000 to 8000 psi with fiber and HRWR.