Project Name: Kendall Soccer Park Renovation
Location: 8011 SW 127 Ave Miami
Project Timeline: Approx 4 months
Completion Date: 12/30/23
Size/Area: 675 square feet
Mix: 3000 PSI, 3000 PSI PR/PM
Owner: Miami Dade County Parks & Recreational
Contractor: Green Engineering & Construction
Sub-contractor: N/A
Supplier: Supermix
Engineer: N/A
Application: Slabs/Sidewalks/Fence Posts, Misc Work
Fiber: N/A
Website Links: N/A

 

Major renovation on actual park, making a difference in the community of Kendall. New sidewalks were poured, fence posts poured. Slab poured for new and improved bleachers and misc. work around the park. Schedule was coordinated around the children’s practice and games.