Project Name: MCMC Braman Cancer Center
Location: 4300 Alton Road Miami Beach
Project Timeline: Approx 1 year
Completion Date: Jan 2025
Size/Area: 200,000 square feet
Mix: Range from 4000 psi to 6000 psi
Owner: Mount Sinai Medical Center
Contractor: Brasfield Gorrie
Supplier: Supermix
Engineer: N/A
Application: N/A
Fiber: N/A
Website Links: N/A

 

This new addition to Mount Sinai Miami Beach is sure to make an impression. The unique design allows all the rooms to have a view while being treated. With options of holistic treatments, massages, meditation classes, physical therapy. All focused around a patient needs and making them feel better. Times of pours were a challenge to coordinate due to patients’ traffic and patient room near by. It’s truly going to be an amazing addition.