Project Name: Tractor Supply
Project Timeline: May 2022 – October 2022
Completion Date: October 2022
Address: Palm City
Supplier: Maschmeyer Concrete
Owner: Tractor Supply Co
Contractor: Dooley Mack
Sub-Contractor: David Mann Construction
Engineer: Thomas Engineering Group
Size/Area: 40,000 sq ft
Mix: 4000 psi
Fiber: Euclid Tuff Strand – 3 lbs/yard

New 40,000 sq ft block building with outside storage area. This locations included a Pet Vet Wellness Center inside the store as well. Total concrete yardage was 1,135 yards with a combined 19,863 split face and regular block.