Project Name: ACC Spec Building
Project Timeline: 6 Months
Completion Date: 9/2/21
Address: Punta Gorda
Supplier: Preferred Materials
Owner: FPC
Contractor: FPC
Sub-Contractor: Keesling Construction
Mix: 5000 PSI
Size/Area: paving – 16,699 
sq. ft.
Engineer: Southern Sun Engineering
Application: Paving
Fiber: Commercial Fiber – 1.5# per yard

We poured 880 yard slab in one pour and then 710 yards of concrete paving in one pour.