[et_pb_section fb_built=”1″ _builder_version=”3.22″][et_pb_row _builder_version=”3.25″ background_size=”initial” background_position=”top_left” background_repeat=”repeat”][et_pb_column type=”4_4″ _builder_version=”3.25″ custom_padding=”|||” custom_padding__hover=”|||”][et_pb_text _builder_version=”4.7.4″ background_size=”initial” background_position=”top_left” background_repeat=”repeat”]

Project Name: Trinity Cancer Center
Project Timeline: 7 Months
Completion Date: 1//20
Location: Trinity, FL
Owner:  The Lunz Group
Supplier: Preferred Materials Inc.
General Contractor: Onicx Contraction
Sub-Contractor: Commercial Concrete Contractors
Size:  37,000 SF
Mix (psi): 4,000
Fiber: Using fiber on the second floor slab poured on metal deck. 4Lbs/CY for Forta Ferro Fiber.
Engineer: TRC Worldwide Engineering
Application: Cancer center radiation vault

New construction of a 37,000 SF 2-Story cancer center. This job consists of 2,000 CY and 22,000 CMU. Project requires 1,000 CY of a high-density granite mix to achieve 147 PCF for the radiation vault. Additionally Conex, a shrinkage reducing admixture, was used in the SOG to meet specifications.

 

[/et_pb_text][/et_pb_column][/et_pb_row][et_pb_row column_structure=”1_2,1_2″ _builder_version=”4.6.6″ _module_preset=”default”][et_pb_column type=”1_2″ _builder_version=”4.6.6″ _module_preset=”default”][dsm_perspective_image src=”https://fcpa.org/wp-content/uploads/Vault1.jpg” title_text=”Vault1″ _builder_version=”4.6.6″ _module_preset=”default”][/dsm_perspective_image][/et_pb_column][et_pb_column type=”1_2″ _builder_version=”4.6.6″ _module_preset=”default”][dsm_perspective_image src=”https://fcpa.org/wp-content/uploads/Vault3.jpg” title_text=”Vault3″ _builder_version=”4.6.6″ _module_preset=”default”][/dsm_perspective_image][/et_pb_column][/et_pb_row][/et_pb_section]