General Contractor – Kast Construction
Project– Channel Club – 23 story Apartments with Cast in Place Garage and Publix Supermarket
Project type – Deep Foundations and Forming
Deep Foundation Contractor – Bauer Foundation
Drilled Shaft Quantity – 4,500 Cubic Yards – 6000 PSI Tremie mix
Forming Subcontractor – Ceco Concrete Construction
Ready-Mix Quantity – 35,000 Cubic Yards
Mix design – 3000 PSI to 8000 PSI
Date – Completed October 2018