I-75 Weigh Stations Paving

Project Name: I-75 Weigh Stations Paving
Location: Punta Gorda
Project Timeline: 8 Weeks
Completion Date: 5/31/2025
Size/Area: 210,000 sq ft
Mix: 3000 PSI
Owner: FDOT
Contractor: Watson Civil
Sub-Contractor: V-Max
Supplier: Preferred Materials
Engineer: N/A
Application: Concrete Paving
Fiber: None
Website Links: N/A

Old paving was milled out of Weigh Station entrances, drive through lanes, and exits. 4 inches of asphalt was placed as a base and 11 inches of concrete on top of the asphalt.