Project Name: Four Fish Marina
Location: 2223 NE Indian River Drive, Jensen Beach
Project Timeline: 4 Months
Completion Date: October 2025
Size/Area: 15,480 Square feet
Mix: 3000 PSI Regular & 6000 PSI Regular
Owner: N/A
Contractor: Cook Shell
Sub-Contractor: N/A
Supplier: Supermix Concrete
Engineer: N/A
Application: SOG
Fiber: N/A
Website Links: N/A
Slab was poured on an early Saturday morning. Coordination, staging of trucks, washout areas were a key on this jobsite. Total Poured was 15,480 square feet with 3 pumps.