Project Name: ALS PS # 3
Location: 7000 W Palmetto Park Unit 102, Boca Raton, FL
Project Timeline: 6 months
Completion Date: August 2025
Size/Area: 3150 SF
Mix: 3000 PSI REGULAR & PR/PM & COURSE GROUT
Owner: N/A
Contractor: CONTIERRA ENGINEERING
Sub-Contractor: N/A
Supplier: SUPERMIX CONCRETE
Engineer: N/A
Application: SOG/Sidewalk/Filling in Trenches
Fiber: N/A
Website Links: N/A
A couple of early morning pours for the SOG/ and speed ramp pours. Mixes used were all 5000 PSI & and square footage was 10,000. Coordination was the key on this jobsite.