Project Name: City of Mt Dora Public Works Facility
Location: Mt Dora, FL
Project Timeline: 12 months
Completion Date: 04/15/2025
Size/Area: 180,000sf
Mix: 4000 PSI
Owner: City of Mt Dora
Contractor: AJAX Construction
Sub-Contractor: BNG Construction
Supplier: Argos USA
Engineer: N/A
Application: Foundation, Sog, Pavement
Fiber: FRC FIB – 300 SYNTHETC FIBER 1.5 lbs/YD
Website Links: N/A
Argos Ready Mix supplied almost 3,000 yards of 4000 psi fiber reinforced concrete to BNG Construction to complete this project. The project included foundations, slab on grade, and paving. The City of Mt Dora choose Ajax construction as the General Contractor. Once completed the new facility will include offices, warehouse/maintenance building and a covered pole barn.